Introduction
Navigating the complexities of construction contracts can be daunting for any business, particularly when the details seem too specialized. As a quantity surveying consultancy, we aim to demystify these complexities, empowering you to make informed decisions. In this blog, we will delve into JCT Construction Contracts, offering a detailed overview of the various contracts within the JCT family, key characteristics influencing contract choice, and crucial aspects like relevant events, relevant matters, loss and expense, partial possession, sectional completion, and insurance options.
What are JCT Contracts?
The Joint Contracts Tribunal (JCT) produces standard forms of contract, guidance notes, and other documents for the construction industry. These contracts are widely used across the UK due to their comprehensive nature and balanced approach, catering to both large-scale and smaller projects.
The JCT Family of Contracts
Key Characteristics Influencing Contract Choice
When selecting a JCT contract, several factors should be considered:
When to Use Each JCT Contract
JCT Standard Building Contract (SBC)
When to Use: Suitable for large or complex projects with detailed contract administration and a need for clear, comprehensive terms. Key Characteristics: Extensive provisions for project size and complexity, risk allocation, and detailed design responsibility. Example: Constructing a new hospital or a multi-story office building where detailed project management and clear risk allocation are essential.
JCT Intermediate Building Contract (IC)
When to Use: Ideal for medium-sized projects that are less complex than those suitable for the Standard Building Contract. Key Characteristics: Suitable for moderate project complexity and risk allocation, with some design responsibility on the contractor. Example: Building a small apartment block or a school extension with moderate design and project management requirements.
JCT Minor Works Building Contract (MW)
When to Use: Best for simple, small-scale projects with minimal complexity. Key Characteristics: Simplified contract for small projects, minimal risk allocation, and straightforward design requirements. Example: Renovating a single retail shop or a small residential refurbishment with minimal complexity.
JCT Design and Build Contract (DB)
When to Use: Suitable for projects where the contractor is responsible for both design and construction. Key Characteristics: Full design and construction responsibility on the contractor, clear risk allocation, and suitable for projects requiring streamlined processes. Example: Developing a new commercial property where the contractor handles both design and construction, providing a single point of responsibility.
JCT Major Project Construction Contract (MP)
When to Use: Tailored for very large, high-value, and complex projects. Key Characteristics: Suitable for high complexity, extensive risk allocation, and detailed project management structure. Example: Construction of a large infrastructure project such as a new airport terminal requiring significant contractual obligations and risk management.
JCT Construction Management Contract (CM)
When to Use: Ideal when a construction manager is appointed to oversee the construction process, with multiple trade contractors. Key Characteristics: Flexible scheduling, detailed project management, and involvement of multiple parties. Example: A complex university campus development where multiple trades and contractors are involved and require coordination.
JCT Management Building Contract (MC)
When to Use: Similar to the Construction Management Contract but the contractor also takes on management tasks. Key Characteristics: Management contractor coordinates the work of various subcontractors, extensive project management involvement. Example: A large residential development where the management contractor oversees and coordinates multiple subcontractors.
JCT Prime Cost Building Contract (PC)
When to Use: Appropriate when the contract sum is not fixed and determined by the cost of work plus a fee. Key Characteristics: Flexibility in pricing, suitable for bespoke projects where exact costs are difficult to predict. Example: A high-end bespoke home renovation where costs need to be flexible due to the unique nature of the project.
JCT Constructing Excellence Contract (CE)
When to Use: Used for projects that aim to integrate teams and promote collaboration to improve project outcomes. Key Characteristics: Emphasis on collaboration, integrated team approach, suitable for innovative and sustainable projects. Example: An innovative public-private partnership project designed to achieve sustainable building practices through team integration.
JCT Measured Term Contract (MTC)
When to Use: Suitable for ongoing maintenance and repair works over a specified period. Key Characteristics: Focus on continuity of work, streamlined administrative processes. Example: Regular maintenance services for a local authority’s housing stock over several years.
JCT Homeowner Contracts (HO)
When to Use: Designed for homeowners engaging contractors for domestic works. Key Characteristics: Simplified process for residential projects, minimal contractual complexity. Example: A homeowner hiring a contractor for a kitchen extension or loft conversion, needing a straightforward contract.
JCT Repair and Maintenance Contract (RMC)
When to Use: Used for smaller repair and maintenance projects requiring straightforward contract terms. Key Characteristics: Simplified approach for ongoing maintenance, minimal administrative burden. Example: Routine maintenance of a commercial property or small-scale repair works needing clear and simple contractual terms.
Relevant Events and Relevant Matters
Relevant Events
Relevant events are events on or off site that impact the completion date of the project works. Examples include:
Force Majeure
Force majeure refers to extraordinary events or circumstances beyond the control of the parties involved that prevent one or both parties from fulfilling their contractual obligations. Common examples include:
Process for Handling Relevant Events
When a relevant event occurs, the following process typically unfolds under JCT contracts:
Associated Timelines
Relevant Matters
Relevant matters are referred to in some construction contracts, such as JCT contracts. A relevant matter is a matter for which the client is responsible that materially affects the progress of the works. This may enable the contractor to claim direct loss and/or expense that has been incurred. Examples include:
Difference Between Relevant Events and Relevant Matters
Loss and Expense
Loss and expense claims arise when the contractor incurs additional costs due to delays or disruptions for which the client is responsible (relevant matter). Loss and expense should be valued as the actual loss incurred by the contractor and not based on schedules of rates or Bills of Quantities (BOQs). Examples of loss and expense claims include:
Partial Possession
Partial possession occurs when the client takes possession of part of the works before completion of the entire project. Here are some key points regarding partial possession:
Sectional Completion
Sectional completion allows for different parts of the project to be completed and handed over at different times. This is particularly useful for phased projects or where different sections of the building have different completion dates. Each section has its own completion date, and liquidated damages can be applied separately for delays to each section.
Comparison: Partial Possession vs. Sectional Completion
Aspect | Partial Possession | Sectional Completion |
Agreement | Requires contractor’s agreement, not usually agreed at contract signing | Agreed upon at the contract signing |
Nature of Possession | Voluntary, can be refused by the contractor if not unreasonably withheld | Planned and scheduled, specified in the contract |
Retention Release | Portion of retention may be released | Retention release typically handled per section |
Insurance Responsibility | Contractor’s insurance ends for the part of the works taken over | Insurance responsibilities as specified for each section |
Liquidated Damages | LADs end for the portion of the works taken over | LADs applied separately for each section |
Employer’s Responsibility | Employer assumes responsibility for damages to the part of the works taken over | Employer assumes responsibility for each completed section |
Defect Liability Period | Commences for the part of the works taken over | Commences for each completed section |
Typical Usage | Used when the employer needs to use part of the project before overall completion, negotiated during the project | Used for phased projects or projects with different completion dates for various sections, specified at the outset |
Insurance Options A, B, and C under JCT
Insurance Option A
Insurance Option B
Insurance Option C
What Are Perils?
Perils refer to specific risks or causes of loss covered by an insurance policy. In construction, these typically include events like fire, theft, vandalism, and natural disasters. Understanding which perils are covered is crucial for managing risk on a construction project.
Common Types of Insurance for Construction Projects
Subrogation and Joint Names Insurance
Subrogation: This is the process by which an insurance company, having paid out a claim, seeks to recover the costs from the party responsible for the loss. In the context of construction contracts, waivers of subrogation are often included to prevent the insurer from seeking recovery from other parties involved in the project, fostering a collaborative environment.
Joint Names Insurance: This type of insurance policy names both the employer and the contractor as insured parties. The main benefits include:
Conclusion
Understanding the intricacies of JCT contracts is essential for any UK construction business. By choosing the appropriate contract, you can ensure that your project is managed efficiently, risks are appropriately allocated, and all parties’ interests are safeguarded. Whether you are embarking on a large-scale project or a small maintenance task, the JCT family of contracts offers a robust framework to support your construction endeavours.
For further guidance on selecting the right JCT contract or managing any aspect of your construction project, feel free to contact our quantity surveying consultancy. We are here to help you navigate these complexities and ensure the success of your construction projects.
Assignment Bill of Quantities Bonds breach Building Contracts Collateral Warranties Construction Act 2009 Consultancy contract contract practice Contracts Contracts (Rights of Third Parties) Act 2009 Cost Plan CW damages Disputes Economic Development and Construction Act 2009 Equitable Assignment FIDIC Force Major Insurance JCT LDEDCA Legal Assignment Letter of Intent LOI NEC NRM Obligations oral Parent Company Guarentee Payless Payment PCG provision Provisions Retention statutory Suspension terms Third Party Rights tort uk Understanding the Local Democracy Warranty